ASCE Guide RainLoadProvisions ASCE 7 16 2020
$32.50
Rain Loads: Guide to the Rain Load Provisions of ASCE 7-16
Published By | Publication Date | Number of Pages |
ASCE | 2020 | 114 |
Rain Loads: Guide to the Rain Load Provision of ASCE 7-16 provides the practicing structural engineer with a detailed description of the rain load provisions of Minimum Design Loads and Associated Criteria for Buildings and Other Structures, Standard ASCE/SEI 7-16.
Authorss O’Rourke and Lewis discuss the key parameters that underpin the provisions and illustrate the application of those provisions. Through more than 35 examples, the correct applications of the rain load provisions are illustrated.
Some roofs are more susceptible than others to rain load problems. In the six chapters, the authors provide a detailed discussion of the rain load hazard; determination of drainage area; head-flow relationships and the associated types of flow; simplified conservative rain load procedures and limits that yield more accurate load estimates; and ponding loads.
When used with the standard, Rain Loads assists engineers in addressing nonroutine rain loading issues that are not explicitly covered in ASCE 7-16.
Rain Loads is an essential supplement to ASCE/SEI Standard 7-16 for all structural engineers, architects, construction professionals, and building officials throughout the United States.
PDF Catalog
PDF Pages | PDF Title |
---|---|
6 | Contents |
10 | Preface Acknowledgments |
12 | Unit Conversions |
79 | 5.1 Equilibrium Approach |
82 | 5.2 Additional Consideration: te > 15 min |
86 | 5.3 Additional Consideration: te <15 min |
90 | Example 5-1. Inflow Rate Table |
91 | Example 5-2. Inflow Rate Equation Example 5-3. Static Head Example 5-4. Hydraulic Head: Dam Example 5-5. Hydraulic Head: Standpipe |
92 | Example 5-6. Rain Load Example 5-7. Rain Load: V-Shaped Drainage Area |
93 | Example 5-8. Maximum Accumulation: Single-Slope Drainage Area Example 5-9. Maximum Accumulation: V-Shaped Drainage Area |
94 | Example 5-10. Maximum Accumulation: Inverted Pyramid Drainage Area Example 5-11. Maximum Accumulation: Flat Drainage Area |
95 | Example 5-12. Time to Overflow |
108 | References |
110 | Index |
114 | About the Authors |