BS EN 13941-2:2019+A1:2021:2022 Edition
$215.11
District heating pipes. Design and installation of thermal insulated bonded single and twin pipe systems for directly buried hot water networks – Installation
Published By | Publication Date | Number of Pages |
BSI | 2022 | 100 |
PDF Catalog
PDF Pages | PDF Title |
---|---|
2 | undefined |
15 | 6.3.1 General |
20 | 10.2.1 Loading and unloading |
21 | 10.2.2 Checking of the delivery 10.3.1 General 10.3.2 Storage of pipe assemblies |
22 | 10.3.3 Storage of fitting and valve assemblies 10.3.4 Storage of joint casing systems and other materials |
23 | 11.3.1 Welding of the steel service pipe and testing of the welds 11.3.1.1 General |
24 | 11.3.1.2 Quality system for the different project classes |
26 | 11.3.1.3 Welding procedures and the welding process 11.3.1.4 Welding consumables 11.3.1.5 Place and position of the weld |
27 | 11.3.1.6 Performance of welding work |
29 | 11.3.1.7 Special procedures |
32 | 11.3.1.8 Documentation |
36 | 11.5.1 General 11.5.2 Visual test with !overpressure” by air |
37 | 11.5.3 Visual test below atmospheric pressure by air 11.5.4 Hydrostatic test 11.5.4.1 General 11.5.4.2 Safety |
38 | 11.5.4.3 Procedures 11.5.4.4 Water as test medium |
39 | 11.5.4.5 Acceptance criteria 11.5.4.6 Leak finding |
40 | 11.5.4.7 Testing equipment 11.5.4.8 Test documentation and records |
41 | 11.5.4.9 Disposal of test water 11.5.4.10 Protection following test 11.6.1 General 11.6.2 Joints 11.6.3 Site prepared components |
47 | 11.11.1 Wall penetrations 11.11.1.1 General 11.11.1.2 Sealing on the building side of the pipe entry 11.11.1.3 Sealing of the casing of the pipe assembly against the pipe entry |
48 | 11.11.2 Connections to other pipe systems 11.11.3 Pipe laying in protection tubes 11.11.4 Protection against external impact for above ground installations |
51 | 15.1.1 Range of application 15.1.2 Documentation — aims and uses |
52 | 15.1.3 Technical documentation 15.1.3.1 General 15.1.3.2 Project documentation |
53 | 15.1.3.3 Test and proof documentation 15.1.3.4 Checklists for technical documentation |
56 | 15.1.4 Drawings of the technical documentation 15.1.4.1 General |
58 | 15.1.4.2 Design plan |
59 | 15.1.4.3 Detailed drawing 15.1.4.4 Pipeline sequence drawing and wiring diagram |
60 | 15.1.5 As-built documentation |
61 | Annex A (informative)Venting and Draining A.1 General A.2 Venting and draining devices |
63 | A.3 Draining devices for large pipeline dimensions |
64 | A.4 Venting of new pipe sections A.4.1 Venting by house connection pipeline |
65 | A.4.2 Venting by venting cabinets |
67 | Annex B (informative)Recommendations for HDD B.1 General B.2 Depth under roads |
68 | B.3 Minimum intermediate distances B.4 Casing and casing field joints B.5 Drilling fluid composition B.6 Drilling fluid pressures |
69 | B.7 Borehole dimensions and borehole stability B.8 Ballasting |
70 | B.9 Installation of pipe bundles B.10 Determination of position and route corrections |
71 | B.11 Registration and control of HDD B.12 Drilling Tolerances |
72 | B.13 Verification of design and methodology for the pullback operation B.14 As-Built information |
73 | Annex C (informative)Qualification of fitters installing joints in pre-insulated bonded pipe networks C.1 Knowledge and skills C.2 Background for training and testing C.3 Subjects for training and testing C.3.1 General |
74 | C.3.2 Casing of polyethylene (PE) C.3.2.1 Important construction characteristics and properties C.3.2.2 Technological behaviour of PE C.3.2.3 Mechanical properties of PE |
75 | C.3.2.4 Conditions for casing elements under load C.3.3 Surveillance C.3.4 PUR-foam system C.3.4.1 PUR-foam as a two component material C.3.4.2 Insulation procedures on job site |
76 | C.3.5 Joint types/jointing systems C.3.5.1 General C.3.5.2 Shrink sleeve joint with mastic/adhesive sealing C.3.5.3 Welded joints/systems |
77 | C.3.6 Installation of joints C.3.6.1 General C.3.6.2 Installation of surveillance system |
78 | C.3.6.3 Sealed joints |
79 | C.3.6.4 Welded joints C.3.6.5 Insulation of joints |
80 | C.3.6.6 Documentation |
81 | Annex D (informative)Quality control program and documentation |
94 | Annex E (normative)Commissioning E.1 Commissioning E.1.1 General |
95 | E.1.2 Filling with water for initial operation E.1.3 Surveillance system |
96 | Annex F (informative)Operation |