This document addresses environmental control within data centres based upon the criteria and classifications for “availability”, “security” and “energy efficiency enablement” within ISO/IEC TS 22237‑1.
This document specifies requirements and recommendations for the following:
-
temperature control;
-
fluid movement control;
-
relative humidity control;
-
particulate control;
-
vibration;
-
floor layout and equipment locations;
-
energy saving practices;
-
physical security of environmental control systems.
Issues related to electromagnetic environment can be found in ISO/IEC TS 22237‑6.
PDF Catalog
PDF Pages | PDF Title |
---|---|
2 | National foreword |
7 | Foreword |
8 | Introduction |
11 | 1 Scope 2 Normative references 3 Terms, definitions and abbreviated terms 3.1 Terms and definitions |
13 | 3.2 Abbreviated terms 4 Conformance 5 Environmental control within data centres 5.1 General 5.1.1 Functional elements |
14 | 5.1.2 Requirements 5.1.3 Recommendations |
15 | 5.2 Environmental control of data centre spaces 5.2.1 Building entrance facilities 5.2.2 Personnel entrance(s) 5.2.3 Docking/loading bay(s) 5.2.4 Generator space(s) including fuel storage 5.2.5 Transformer space(s) |
16 | 5.2.6 Electrical distribution space(s) 5.2.7 Telecommunication spaces(s) 5.2.8 Main distributor spaces(s) 5.2.9 Computer room space(s) and associated testing space(s) |
17 | 5.2.10 Electrical space(s) 5.2.11 Mechanical space(s) 5.2.12 Control room space(s) 5.2.13 Office space(s) 5.2.14 Storage and holding space(s) 5.2.15 Accommodation of UPS equipment |
18 | 6 Availability 6.1 General 6.2 Design options by space 6.2.1 General |
19 | 6.2.2 Spaces excluded from the availability classification 6.2.3 Main distributor space(s) |
20 | 6.2.4 Computer room space(s) and associated testing space(s) |
21 | 6.2.5 UPS space |
22 | 6.3 Environmental control system capacity planning with respect to expansion 6.4 Environmental control system capacity planning with respect to resilience 7 Physical security 7.1 General 7.2 Access 8 Energy efficiency enablement 8.1 General 8.2 Measurement of temperature 8.2.1 External temperature |
23 | 8.2.2 Computer room temperature |
24 | 8.3 Measurement of relative humidity 8.3.1 External relative humidity 8.3.2 Computer room relative humidity |
25 | 8.4 Measurement of air pressure 8.5 Coolant flow rates 8.6 Heat removal 8.7 Outside air 8.8 Provision of alarms 8.9 Measurement requirements by Granularity Level |
27 | Annex A (normative) Distribution methodologies for temperature-controlled airin computer room space |
30 | Annex B (informative) Control system concepts |