Shopping Cart

No products in the cart.

BSI PD IEC TS 63042-102:2021:2024 Edition

$198.66

UHV AC transmission systems – General system design

Published By Publication Date Number of Pages
BSI 2024 70
Guaranteed Safe Checkout
Categories: ,

If you have any questions, feel free to reach out to our online customer service team by clicking on the bottom right corner. Weโ€™re here to assist you 24/7.
Email:[email protected]

PDF Catalog

PDF Pages PDF Title
2 undefined
4 CONTENTS
8 FOREWORD
10 INTRODUCTION
11 1 Scope
2 Normative references
3 Terms and definitions
4 Objective and key issues of UHV AC transmission application
4.1 Objective
12 4.2 Key application issues
5 Required studies on UHV AC system planning and design
5.1 General
13 5.2 Required studies
5.3 Required analysis tools
14 Figures
Figure 1 โ€“ Analysis tool by time domain
15 6 UHV AC system planning
6.1 General
6.1.1 Introductory remarks
6.1.2 Transmission capacity considering routes and line types to use
6.1.3 Reactive power management issues
16 6.1.4 Environmental issues
Figure 2 โ€“ Flowchart of reactive power compensation configuration
17 6.2 Scenario for system planning
6.3 Scenario for network planning procedure
6.3.1 Power transmission capacity
Figure 3 โ€“ ฯ€ equivalent circuit
18 6.3.2 System voltage
6.3.3 Route selection
19 6.3.4 Series compensation
6.4 Required parameters
6.5 Transmission network (topology)
20 6.6 Reliability
21 7 UHV AC system design
7.1 General
7.2 Reactive power management
7.3 Reclosing schemes
22 Figure 4 โ€“ Four-legged reactor
23 7.4 Delayed current zero phenomenon
Figure 5 โ€“ One typical reclosing sequence of high speed earthing switches (HSESs)
Tables
Table 1 โ€“ Specification of reclosing scheme
24 7.5 Protection and control system
7.6 Insulation design (cost effectiveness)
25 Figure 6 โ€“ Procedure for insulation design
26 Annex A (informative)History of development of UHV AC transmission technologies
A.1 General
A.2 History of development in the USA
A.3 History of development in former USSR and Russia
A.4 History of development in Italy
27 A.5 History of development in Japan
A.6 History of development in China
A.7 History of development in India
28 Annex B (informative)Experiences relating to UHV AC transmission development
B.1 Project development in Italy
B.1.1 Background (including network development)
B.1.2 Demand analysis and scenario of application
B.1.3 Project overview
Figure B.1 โ€“ Demand situation in Italy
29 B.1.4 UHV system planning
Figure B.2 โ€“ UHV transmission lines in Italy as originally planned in ’70
30 B.1.5 UHV system design
Figure B.3 โ€“ SPIRA system and SICRE system
31 B.1.6 Laboratory and field tests
Figure B.4 โ€“ Preliminary system design
32 Figure B.5 โ€“ Field testing of UHV equipment
Table B.1 โ€“ Specifications of 1 100 kV transformer
33 Table B.2 โ€“ Specifications of pilot plant (substation)
Table B.3 โ€“ Specifications of pilot plant (cable)
34 B.2 Project development in China
B.2.1 Background
B.2.2 Project overview
Figure B.6 โ€“ UHV AC transmission projects implemented in China
35 B.2.3 Changzhi-Nanyang-Jingmen UHV AC extension project
Figure B.7 โ€“ Single-line diagram of Changzhi-Nanyang-Jingmen UHV AC pilot project
Table B.4 โ€“ Parameters of substation and switching station of Changzhi-Nanyang-Jingmen UHV AC pilot project
Table B.5 โ€“ Parameters of transmission lines of Changzhi-Nanyang-Jingmen UHV AC pilot project
36 Figure B.8 โ€“ Artificial grounding test of UHV series capacitors in China
Figure B.9 โ€“ Single-line diagram of Huainan-Zhebei-Shanghai double-circuit UHV AC project
37 B.2.4 Overvoltage mitigation and insulation coordination
Figure B.10 โ€“ Generator integrated into a UHV system through a UHV step-up transformer
Table B.6 โ€“ Main system parameters of UHV AC projects in China
38 B.2.5 Insulation coordination
Table B.7 โ€“ Main system parameters of UHV arrester
39 Table B.8 โ€“ Required minimum value of clearance of the 1 100 kV transmission line
Table B.9 โ€“ Minimum clearance of UHV substation (metres)
40 B.2.6 Laboratory and field tests
Figure B.11 โ€“Hubei Wuhan UHV AC test base
Figure B.12 โ€“Hebei Bazhou UHV tower test base
Table B.10 โ€“ Overvoltage withstand level of UHV AC projects in China
42 B.3 Project development in India
B.3.1 Background (including network development)
B.3.2 Demand analysis and scenario of application
B.3.3 Project overview
43 B.3.4 Development of 1 200 kV national test station in India
Figure B.13 โ€“ 1 200 kV national test station (India)
44 B.3.5 POWERGRID’s 1 200 kV transmission system
Figure B.14 โ€“ Power flow from Satna to Bina diverted via a 1 200 kV test station (India)
45 B.3.6 UHV AC technology design โ€“ Insulation coordination
Figure B.15 โ€“ Schematic of 1 200 kV UHV AC line
Table B.11 โ€“ Basic technical parameters for 1 200 kV UHV AC system selected in India
46 B.3.7 Insulation design for substation
Figure B.16 โ€“ Typical V-I characteristic of 1 200 kV MOSA
47 B.4 Project development in Japan
B.4.1 Background (including network development)
Figure B.17 โ€“ Sequence of events for calculation of surge arrester energy accumulation
Table B.12 โ€“ TOV and energy absorption by surge arrester
48 B.4.2 Demand analysis and scenario of application
B.4.3 Project overview
Figure B.18 โ€“ Trend of peak demand in Japan
49 B.4.4 UHV system planning
B.4.5 UHV system design
Figure B.19 โ€“ UHV transmission line for each construction year in Japan
Figure B.20 โ€“ Concept for transmission capacity enhancement with short-circuit current restriction
50 Figure B.21 โ€“ Insulation design sequence of 1 100 kV transmission lines’ air gap clearances
51 Figure B.22 โ€“ UHV designed transmission line in TEPCO
Table B.13 โ€“ Requirement against large charging MVA
Table B.14 โ€“ Specifications of substation insulation design
52 B.4.6 Laboratory and field tests
Figure B.23 โ€“ Field testing of UHV substation equipment since 1996
Table B.15 โ€“ Specifications of 1 100 kV transformer
53 Table B.16 โ€“ Specifications of 1 100 kV GIS
Table B.17 โ€“ Example of field test โ€“ Measurement items of transformer
54 Table B.18 โ€“ Example of field test โ€“ Measurement items of GIS
55 Annex C (informative)Summary of system technologies specific to UHV AC transmission systems
C.1 Technologies used in China
C.1.1 Transformer
Figure C.1 โ€“ UHV AC transformer
Table C.1 โ€“ Main parameters of UHV AC typical transformer
56 C.1.2 UHV shunt reactor and reactive compensation at tertiary side of transformer
Figure C.2 โ€“ UHV AC shunt reactor
Table C.2 โ€“ Main parameters of UHV AC reactive power compensation equipment
57 C.1.3 Switchgear
Figure C.3 โ€“ Reactor and capacitor at tertiary side of UHV transformer
Table C.3 โ€“ Main parameters of UHV AC circuit-breaker
58 Figure C.4 โ€“ UHV GIS
Figure C.5 โ€“ UHV MTS
59 C.1.4 Series capacitor (SC)
Figure C.6 โ€“ UHV air insulated disconnectors
60 Figure C.7 โ€“ Single-line diagram of UHV series capacitor
Figure C.8 โ€“ UHV series capacitor
Table C.4 โ€“ Rated values of UHV SCs in Changzhi-Nanyang-Jingmen UHV extension project
61 C.1.5 Gas-insulated transmission line (GIL)
Figure C.9 โ€“ UHV GIL tunnel below Yangtze River
Figure C.10 โ€“ Inside a UHV GIL tunnel during assembly
62 C.2 Technologies used in India
C.2.1 UHV AC transformer
Table C.5 โ€“ Specifications of 333 MVA transformer for the 1 200 kV test station
63 C.2.2 Surge arrester
Figure C.11 โ€“ 333 MVA transformer for the 1 200 kV test station
Table C.6 โ€“ Technical specifications of surge arrester
64 C.2.3 Circuit-breakers
Figure C.12 โ€“ First prototype of 850 kV surge arrester for 1 200 kV system
Table C.7 โ€“ Technical parameters of UHV circuit-breaker
65 C.2.4 Instrument transformers
Figure C.13 โ€“ UHV circuit-breaker in India
Table C.8 โ€“ Parameters of instrument transformer
66 C.3 Technologies used in Japan
C.3.1 Switch gear
Figure C.14 โ€“ Instrument transformer
67 C.3.2 Surge arrester
Figure C.15 โ€“ 1 100 kV gas circuit-breaker
Figure C.16 โ€“ Resistor-assisted disconnecting operation
Table C.9 โ€“ Specification of gas circuit-breaker
68 Figure C.17 โ€“ Surge arrester with low protection level
Table C.10 โ€“ Specifications of surge arrester
69 Bibliography
BSI PD IEC TS 63042-102:2021
$198.66