IEEE 336 2010
$37.38
IEEE Recommended Practice for Installation, Inspection, and Testing for Class 1E Power, Instrumentation, and Control Equipment at Nuclear Facilities
Published By | Publication Date | Number of Pages |
IEEE | 2010 | 25 |
Revision Standard – Active. Considerations for the pre-installation, installation, inspection, and testing of Class 1E power, instrumentation, and control equipment and systems of a nuclear facility while in the process of installing, inspecting, and testing during new construction, modification, or maintenance are provided. This recommended practice does not apply to periodic testing. For purposes of this standard, in addition to a nuclear power plant, a nuclear facility is defined as a facility related to the nuclear fuel cycle from fuel processing to reprocessing and waste facilities.
PDF Catalog
PDF Pages | PDF Title |
---|---|
1 | IEEE Std 336-2010 (Revision of IEEE Std 336-2005) Front cover |
3 | Title page |
6 | Introduction |
7 | Notice to users Laws and regulations Copyrights Updating of IEEE documents Errata Interpretations |
8 | Patents Participants |
11 | Contents |
13 | Important notice 1. Overview 1.1 Scope 1.2 Purpose |
14 | 1.3 Applicability 1.4 Responsibility 2. Normative references |
15 | 3. Definitions 4. General considerations for initial construction, modification, and maintenance 4.1 General |
16 | 4.2 Configuration management 4.3 Planning |
17 | 4.4 Closeout tracking 4.5 Procedures |
18 | 4.6 Measuring and test equipment 4.7 Personnel qualification 4.8 Test data evaluation 4.9 Results 4.10 Nonconforming items 4.11 Records |
19 | 5. Pre-installation constructability review 6. Installation/construction 6.1 Equipment placement 6.2 Engineering procedures and specifications |
20 | 6.3 Verification during installation 6.4 Post-installation inspections |
21 | 6.5 Inspections of temporary conditions 7. Testing 7.1 General 7.2 Material source testing 7.3 Electrical tests |
22 | 7.4 Radiation and chemical tests 7.5 Mechanical tests 7.6 Equipment tests |
23 | 7.7 System tests 7.8 Post-modification/maintenance testing plan (PMTP) |
24 | 8. Supplementary provisions for multi-unit facilities 8.1 General 8.2 Planning and preparation 8.3 Work tagging considerations 8.4 Protection of existing unit(s) 8.5 Common area caution |
25 | Annex A (informative) Bibliography |